Linde and ITM Power Timeline of Events
Supplementary information for the articles:
| Date |
Event |
| January 18, 2018 |
REFHYNE 10 MW electrolyzer at Shell Wesseling announced |
| October 23, 2019 |
Linde acquires ITM Power shares, joint venture ITM Linde Electrolysis created |
| January 13, 2021 |
Announcement of 24 MW electrolyzer in Leuna |
| March 08, 2021 |
Linde Leuna to supply Hydrogen ferry MF Hydra by Norled in Norway |
| July 01, 2021 |
Inauguration of Shell REFHYNE electrolyzer |
| January 28, 2022 |
ITM announces 24 Megawatt electrolyzer sale to Yara Porsgrunn |
| September, 2022 |
First start-up attempt of Leuna electrolyzer suspended due to safety issue |
| September 30, 2022 |
ITM Annual report 2022 reveals delay at Leuna project |
| June 06, 2023 |
MDR reports about delay of Electrolyzer in Leuna |
| June 29, 2023 |
Christening of Norled ferry MF Hydra |
| June 10, 2024 |
Yara inaugurates electrolyzer in Porsgrunn |
| August 12, 2024 |
RWE inaugurates 4 MW electrolyzer in Lingen |
| August 15, 2024 |
Mention of "commercial dispute" in ITM Power interim report |
| August 19, 2024 |
REFHYNE II 100 MW electrolyzer at Shell Wesseling announced |
| August 29, 2024 |
ITM Power annual report reveals ITM Linde Electrolysis GmbH will not take up any further work |
| August 26, 2024 |
Accident at Hydrogen trailer in Leuna |
| October 25, 2024 |
Yara shelves full conversion to green Hydrogen in Porsgrunn |
| January 30, 2025 |
ITM Power interim report reveals dispute with Linde concluded, 13m GBP payment from ITM Power to Linde |
| August 13, 2025 |
Linde receives grant for 5 MW alkaline electrolyzer in Leuna |
| December, 2025 |
Accident with hydrogen leak and fire at Leuna electrolyzer |
| August 04, 2026 |
First Hydrogen from RWE Lingen delivered to customers |
You can find this article online at https://industrydecarbonization.com/misc/lindeitmtimeline.html
Created: